Q5 Wrongside Failures
|
|
08-09-2011, 10:25 PM
(This post was last modified: 15-09-2011 07:30 PM by PJW.)
|
|||
|
|||
|
Q5 Wrongside Failures
Question 5.
Describe two signalling or telecommunication wrong side failures (WSFs) that occur on railway infrastructure. [6 marks] Explain the possible consequences of each of the WSFs that you have described. [8 marks] Describe how both procedural and technical solutions can be adopted to minimise the risk of future occurrences of each of the WSFs you have described. [11 marks] Extremely popular question 6/8 attempts PJW |
|||
|
15-09-2011, 07:33 PM
(This post was last modified: 15-09-2011 08:11 PM by PJW.)
|
|||
|
|||
|
RE: Q5 Wrongside Failures
PJW |
|||
|
« Next Oldest | Next Newest »
|